Montgomery County's SB just approved a contract for building a new Blacksburg High, a new Auburn High, and renovations to make AHS the new AMS, and their numbers don't look like what Wise Co. is tossing around.
Branch & Associates says the 600 student, 175,000 sq. ft. Auburn High BUILDING will cost $26.1 Mil.
Add in their other stuff and it comes to $35.6 Mil.
Add in, oh, a quarter of the $14 Mil. "furnishings" cost, or $3.5 Mil., and Auburn's ACTUAL cost is $39 Mil.
(and this is less than $44.6 Mil. that had been proposed before BHS' gym roof collapsed.)
Wise is saying a 750-student HS for $25 Mil... right?
How will they do it?
Montgomery County school board OKs construction for 3 new schools - Roanoke.com